Roads & HighwaysIPM · Central Project#618173

Shirur-Kharda section from 55937 km to 114486 km to 2LPS/4L

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹382 CrUtilization: 68.6%

Original Cost

₹382 Cr

Baseline estimate

On budget

Revised Cost

₹382 Cr

Latest approved cost

Expenditure

₹262 Cr

Spent to date

Utilization

68.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹120 Cr

Budget left

Budget Utilization

68.6%
0%25%50%75%100%

Spent

₹262 Cr

Remaining

₹120 Cr

Total

₹382 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

16/06/2019

Revised Completion

30/08/2026

Completed

Project Details

Project Code618173
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹382 Cr
Revised Cost₹382 Cr
Expenditure₹262 Cr
Original End Date16/06/2019
Revised Date30/08/2026

Project Intelligence

Project is within original budget of ₹382 Cr — no cost escalation recorded.

Expenditure stands at ₹262 Cr, which is 68.6% of the revised project cost.

Remaining budget: ₹120 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Shirur-Kharda section from 55937 km to 114486 km to 2LPS/4L is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹382.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Shirur-Kharda section from 55937 km to 114486 km to 2LPS/4L"?
Shirur-Kharda section from 55937 km to 114486 km to 2LPS/4L is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹382 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹382 Cr has not been significantly revised. Expenditure: ₹262 Cr (68.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Shirur-Kharda section from 55937 km to 114486 km to 2LPS/4L is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618173. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Shirur-Kharda section from 55937 km to 114486 km to 2LPS/4L is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.