Water ResourcesIPM · Central Project +18.8% overrun#701411

Shahpur Kandi Dam Project

Department of Water Resources, River Development & GRPunjab
Revised Cost: ₹2716 CrUtilization: 81.1%Overrun: +₹430 Cr

Original Cost

₹2286 Cr

Baseline estimate

+19% overrun

Revised Cost

₹2716 Cr

Latest approved cost

Expenditure

₹2202 Cr

Spent to date

Utilization

81.1%

Of revised budget

Escalated

Cost Status

+18.8%

+₹430 Cr increase

Remaining

₹514 Cr

Budget left

Budget Utilization

81.1%
0%25%50%75%100%

Spent

₹2202 Cr

Remaining

₹514 Cr

Total

₹2716 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2286 Cr

Revised Cost

₹2716 Cr

Increase

+₹430 Cr

Escalation

+18.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2022

Revised Completion

30/06/2026

Completed

Project Details

Project Code701411
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹2286 Cr
Revised Cost₹2716 Cr
Expenditure₹2202 Cr
Original End Date30/06/2022
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹430 Cr (18.8%) from the original estimate of ₹2286 Cr.

Expenditure stands at ₹2202 Cr, which is 81.1% of the revised project cost.

Remaining budget: ₹514 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Shahpur Kandi Dam Project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹2286.00 Cr, later revised to ₹2715.70 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Shahpur Kandi Dam Project"?
Shahpur Kandi Dam Project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Punjab. Original cost: ₹2286 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2286 Cr and has been revised to ₹2716 Cr — a cost overrun of +18.8%. Expenditure to date: ₹2202 Cr (81.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Shahpur Kandi Dam Project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 701411. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Shahpur Kandi Dam Project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.