Shahpur Kandi Dam Project
Original Cost
₹2286 Cr
Baseline estimate
Revised Cost
₹2716 Cr
Latest approved cost
Expenditure
₹2202 Cr
Spent to date
Utilization
81.1%
Of revised budget
Cost Status
+18.8%
+₹430 Cr increase
Remaining
₹514 Cr
Budget left
Budget Utilization
81.1%Spent
₹2202 Cr
Remaining
₹514 Cr
Total
₹2716 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2286 Cr
Revised Cost
₹2716 Cr
Increase
+₹430 Cr
Escalation
+18.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/06/2022
Revised Completion
30/06/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹430 Cr (18.8%) from the original estimate of ₹2286 Cr.
Expenditure stands at ₹2202 Cr, which is 81.1% of the revised project cost.
Remaining budget: ₹514 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.
Shahpur Kandi Dam Project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹2286.00 Cr, later revised to ₹2715.70 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Shahpur Kandi Dam Project"?
- Shahpur Kandi Dam Project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Punjab. Original cost: ₹2286 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2286 Cr and has been revised to ₹2716 Cr — a cost overrun of +18.8%. Expenditure to date: ₹2202 Cr (81.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Shahpur Kandi Dam Project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 701411. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Shahpur Kandi Dam Project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.