Original Cost
₹2286 Cr
Baseline estimate
Revised Cost
₹2716 Cr
Latest approved cost
Expenditure
₹2202 Cr
Spent to date
Utilization
81.1%
Of revised budget
Cost Status
+18.8%
+₹430 Cr increase
Remaining
₹514 Cr
Budget left
Spent
₹2202 Cr
Remaining
₹514 Cr
Total
₹2716 Cr
Original Cost
₹2286 Cr
Revised Cost
₹2716 Cr
Increase
+₹430 Cr
Escalation
+18.8%
Project Approved
Construction / Implementation
Original End Date
30/06/2022
Revised Completion
30/06/2026
Completed
Cost has increased by ₹430 Cr (18.8%) from the original estimate of ₹2286 Cr.
Expenditure stands at ₹2202 Cr, which is 81.1% of the revised project cost.
Remaining budget: ₹514 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.