Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumption at MR
Original Cost
₹483 Cr
Baseline estimate
Revised Cost
₹483 Cr
Latest approved cost
Expenditure
₹381 Cr
Spent to date
Utilization
78.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹102 Cr
Budget left
Budget Utilization
78.9%Spent
₹381 Cr
Remaining
₹102 Cr
Total
₹483 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/04/2027
Revised Completion
30/04/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹483 Cr — no cost escalation recorded.
Expenditure stands at ₹381 Cr, which is 78.9% of the revised project cost.
Remaining budget: ₹102 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Energy Storage. Ministry: Ministry of Petroleum & Natural Gas.
Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumption at MR is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Energy Storage sector. The original approved cost is ₹483.00 Cr, later revised to ₹483.14 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumpt"?
- Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumption at MR is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Energy Storage. State: Maharashtra. Original cost: ₹483 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹483 Cr has not been significantly revised. Expenditure: ₹381 Cr (78.9% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant is under the Ministry of Petroleum & Natural Gas in the Energy Storage sector. Project code: 619313. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant is one of several Bihar projects tracked under the Energy Storage sector on the IPM system.