Energy StorageIPM · Central Project#619313

Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumption at MR

Ministry of Petroleum & Natural GasMaharashtra
Revised Cost: ₹483 CrUtilization: 78.9%

Original Cost

₹483 Cr

Baseline estimate

On budget

Revised Cost

₹483 Cr

Latest approved cost

Expenditure

₹381 Cr

Spent to date

Utilization

78.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹102 Cr

Budget left

Budget Utilization

78.9%
0%25%50%75%100%

Spent

₹381 Cr

Remaining

₹102 Cr

Total

₹483 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/04/2027

Revised Completion

30/04/2027

Completed

Project Details

Project Code619313
SectorEnergy Storage
MinistryMinistry of Petroleum & Natural Gas
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹483 Cr
Revised Cost₹483 Cr
Expenditure₹381 Cr
Original End Date30/04/2027
Revised Date30/04/2027

Project Intelligence

Project is within original budget of ₹483 Cr — no cost escalation recorded.

Expenditure stands at ₹381 Cr, which is 78.9% of the revised project cost.

Remaining budget: ₹102 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Energy Storage. Ministry: Ministry of Petroleum & Natural Gas.

Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumption at MR is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Energy Storage sector. The original approved cost is ₹483.00 Cr, later revised to ₹483.14 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumpt"?
Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant for Captive Consumption at MR is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Energy Storage. State: Maharashtra. Original cost: ₹483 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹483 Cr has not been significantly revised. Expenditure: ₹381 Cr (78.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant is under the Ministry of Petroleum & Natural Gas in the Energy Storage sector. Project code: 619313. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Setting up of 50 MW [plus/minus 5 percent] Wind Power Plant is one of several Bihar projects tracked under the Energy Storage sector on the IPM system.