Original Cost
₹240 Cr
Baseline estimate
Revised Cost
₹240 Cr
Latest approved cost
Expenditure
₹148 Cr
Spent to date
Utilization
61.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹92 Cr
Budget left
Spent
₹148 Cr
Remaining
₹92 Cr
Total
₹240 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹240 Cr — no cost escalation recorded.
Expenditure stands at ₹148 Cr, which is 61.6% of the revised project cost.
Remaining budget: ₹92 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Energy Storage. Ministry: Ministry of Petroleum & Natural Gas.