Original Cost
₹2900 Cr
Baseline estimate
Revised Cost
₹2900 Cr
Latest approved cost
Expenditure
₹1206 Cr
Spent to date
Utilization
41.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1693 Cr
Budget left
Spent
₹1206 Cr
Remaining
₹1693 Cr
Total
₹2900 Cr
Project Approved
Construction / Implementation
Original End Date
04/10/2022
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹2900 Cr — no cost escalation recorded.
Expenditure stands at ₹1206 Cr, which is 41.6% of the revised project cost.
Remaining budget: ₹1693 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.