Original Cost
₹1673 Cr
Baseline estimate
Revised Cost
₹1673 Cr
Latest approved cost
Expenditure
₹22 Cr
Spent to date
Utilization
1.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1651 Cr
Budget left
Spent
₹22 Cr
Remaining
₹1651 Cr
Total
₹1673 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹1673 Cr — no cost escalation recorded.
Expenditure stands at ₹22 Cr, which is 1.3% of the revised project cost.
Remaining budget: ₹1651 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.