Original Cost
₹5022 Cr
Baseline estimate
Revised Cost
₹6670 Cr
Latest approved cost
Expenditure
₹4957 Cr
Spent to date
Utilization
74.3%
Of revised budget
Cost Status
+32.8%
+₹1648 Cr increase
Remaining
₹1713 Cr
Budget left
Spent
₹4957 Cr
Remaining
₹1713 Cr
Total
₹6670 Cr
Original Cost
₹5022 Cr
Revised Cost
₹6670 Cr
Increase
+₹1648 Cr
Escalation
+32.8%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/03/2026
Completed
Cost has increased by ₹1648 Cr (32.8%) from the original estimate of ₹5022 Cr.
Expenditure stands at ₹4957 Cr, which is 74.3% of the revised project cost.
Remaining budget: ₹1713 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.