Original Cost
₹353 Cr
Baseline estimate
Revised Cost
₹1023 Cr
Latest approved cost
Expenditure
₹873 Cr
Spent to date
Utilization
85.3%
Of revised budget
Cost Status
+189.9%
+₹670 Cr increase
Remaining
₹151 Cr
Budget left
Spent
₹873 Cr
Remaining
₹151 Cr
Total
₹1023 Cr
Original Cost
₹353 Cr
Revised Cost
₹1023 Cr
Increase
+₹670 Cr
Escalation
+189.9%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
30/06/2026
Completed
Cost has increased by ₹670 Cr (189.9%) from the original estimate of ₹353 Cr.
Expenditure stands at ₹873 Cr, which is 85.3% of the revised project cost.
Remaining budget: ₹151 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.