Original Cost
₹752 Cr
Baseline estimate
Revised Cost
₹765 Cr
Latest approved cost
Expenditure
₹570 Cr
Spent to date
Utilization
74.4%
Of revised budget
Cost Status
+1.8%
+₹13 Cr increase
Remaining
₹196 Cr
Budget left
Spent
₹570 Cr
Remaining
₹196 Cr
Total
₹765 Cr
Original Cost
₹752 Cr
Revised Cost
₹765 Cr
Increase
+₹13 Cr
Escalation
+1.8%
Project Approved
Construction / Implementation
Original End Date
09/08/2023
Revised Completion
15/06/2026
Completed
Cost has increased by ₹13 Cr (1.8%) from the original estimate of ₹752 Cr.
Expenditure stands at ₹570 Cr, which is 74.4% of the revised project cost.
Remaining budget: ₹196 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.