Roads & HighwaysIPM · Central Project +1.8% overrun#618614

Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K AJ-RGBS-Package-3

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹765 CrUtilization: 74.4%Overrun: +₹13 Cr

Original Cost

₹752 Cr

Baseline estimate

+2% overrun

Revised Cost

₹765 Cr

Latest approved cost

Expenditure

₹570 Cr

Spent to date

Utilization

74.4%

Of revised budget

Escalated

Cost Status

+1.8%

+₹13 Cr increase

Remaining

₹196 Cr

Budget left

Budget Utilization

74.4%
0%25%50%75%100%

Spent

₹570 Cr

Remaining

₹196 Cr

Total

₹765 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹752 Cr

Revised Cost

₹765 Cr

Increase

+₹13 Cr

Escalation

+1.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/08/2023

Revised Completion

15/06/2026

Completed

Project Details

Project Code618614
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-05

Financial Summary

Original Cost₹752 Cr
Revised Cost₹765 Cr
Expenditure₹570 Cr
Original End Date09/08/2023
Revised Date15/06/2026

Project Intelligence

Cost has increased by ₹13 Cr (1.8%) from the original estimate of ₹752 Cr.

Expenditure stands at ₹570 Cr, which is 74.4% of the revised project cost.

Remaining budget: ₹196 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K AJ-RGBS-Package-3 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹752.00 Cr, later revised to ₹765.25 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K AJ-RGBS-Package-3"?
Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K AJ-RGBS-Package-3 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹752 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹752 Cr and has been revised to ₹765 Cr — a cost overrun of +1.8%. Expenditure to date: ₹570 Cr (74.4% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K A is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618614. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K A is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.