RailwaysIPM · Central Project#615915

Rourkela-Bondamunda A-Cabin 5th line 10 km Umbrella work PB57/2019-20/NR

Ministry of RailwaysOdisha
Revised Cost: ₹245 CrUtilization: 66.3%

Original Cost

₹245 Cr

Baseline estimate

On budget

Revised Cost

₹245 Cr

Latest approved cost

Expenditure

₹162 Cr

Spent to date

Utilization

66.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹83 Cr

Budget left

Budget Utilization

66.3%
0%25%50%75%100%

Spent

₹162 Cr

Remaining

₹83 Cr

Total

₹245 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2024

Revised Completion

30/11/2026

Completed

Project Details

Project Code615915
SectorRailways
MinistryMinistry of Railways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹245 Cr
Revised Cost₹245 Cr
Expenditure₹162 Cr
Original End Date30/09/2024
Revised Date30/11/2026

Project Intelligence

Project is within original budget of ₹245 Cr — no cost escalation recorded.

Expenditure stands at ₹162 Cr, which is 66.3% of the revised project cost.

Remaining budget: ₹83 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Rourkela-Bondamunda A-Cabin 5th line 10 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹245.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rourkela-Bondamunda A-Cabin 5th line 10 km Umbrella work PB57/2019-20/NR"?
Rourkela-Bondamunda A-Cabin 5th line 10 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹245 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹245 Cr has not been significantly revised. Expenditure: ₹162 Cr (66.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rourkela-Bondamunda A-Cabin 5th line 10 km Umbrella work PB5 is under the Ministry of Railways in the Railways sector. Project code: 615915. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rourkela-Bondamunda A-Cabin 5th line 10 km Umbrella work PB5 is one of several Bihar projects tracked under the Railways sector on the IPM system.