Original Cost
₹245 Cr
Baseline estimate
Revised Cost
₹245 Cr
Latest approved cost
Expenditure
₹82 Cr
Spent to date
Utilization
33.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹163 Cr
Budget left
Spent
₹82 Cr
Remaining
₹163 Cr
Total
₹245 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2026
Revised Completion
26/09/2026
Completed
Project is within original budget of ₹245 Cr — no cost escalation recorded.
Expenditure stands at ₹82 Cr, which is 33.5% of the revised project cost.
Remaining budget: ₹163 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.