Original Cost
₹352 Cr
Baseline estimate
Revised Cost
₹352 Cr
Latest approved cost
Expenditure
₹326 Cr
Spent to date
Utilization
92.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹26 Cr
Budget left
Spent
₹326 Cr
Remaining
₹26 Cr
Total
₹352 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2027
Revised Completion
27/06/2027
Completed
Project is within original budget of ₹352 Cr — no cost escalation recorded.
Expenditure stands at ₹326 Cr, which is 92.6% of the revised project cost.
Remaining budget: ₹26 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.