Original Cost
₹463 Cr
Baseline estimate
Revised Cost
₹501 Cr
Latest approved cost
Expenditure
₹318 Cr
Spent to date
Utilization
63.6%
Of revised budget
Cost Status
+8.1%
+₹38 Cr increase
Remaining
₹182 Cr
Budget left
Spent
₹318 Cr
Remaining
₹182 Cr
Total
₹501 Cr
Original Cost
₹463 Cr
Revised Cost
₹501 Cr
Increase
+₹38 Cr
Escalation
+8.1%
Project Approved
Construction / Implementation
Original End Date
31/12/2025
Revised Completion
30/06/2027
Completed
Cost has increased by ₹38 Cr (8.1%) from the original estimate of ₹463 Cr.
Expenditure stands at ₹318 Cr, which is 63.6% of the revised project cost.
Remaining budget: ₹182 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.