Original Cost
₹622 Cr
Baseline estimate
Revised Cost
₹622 Cr
Latest approved cost
Expenditure
₹220 Cr
Spent to date
Utilization
35.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹402 Cr
Budget left
Spent
₹220 Cr
Remaining
₹402 Cr
Total
₹622 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹622 Cr — no cost escalation recorded.
Expenditure stands at ₹220 Cr, which is 35.4% of the revised project cost.
Remaining budget: ₹402 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.