Roads & HighwaysIPM · Central Project +34.7% overrun#618700

Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹2510 CrUtilization: 67.3%Overrun: +₹647 Cr

Original Cost

₹1863 Cr

Baseline estimate

+35% overrun

Revised Cost

₹2510 Cr

Latest approved cost

Expenditure

₹1689 Cr

Spent to date

Utilization

67.3%

Of revised budget

Escalated

Cost Status

+34.7%

+₹647 Cr increase

Remaining

₹821 Cr

Budget left

Budget Utilization

67.3%
0%25%50%75%100%

Spent

₹1689 Cr

Remaining

₹821 Cr

Total

₹2510 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1863 Cr

Revised Cost

₹2510 Cr

Increase

+₹647 Cr

Escalation

+34.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/01/2024

Revised Completion

30/09/2026

Completed

Project Details

Project Code618700
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1863 Cr
Revised Cost₹2510 Cr
Expenditure₹1689 Cr
Original End Date31/01/2024
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹647 Cr (34.7%) from the original estimate of ₹1863 Cr.

Expenditure stands at ₹1689 Cr, which is 67.3% of the revised project cost.

Remaining budget: ₹821 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1863.00 Cr, later revised to ₹2510.14 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71"?
Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹1863 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1863 Cr and has been revised to ₹2510 Cr — a cost overrun of +34.7%. Expenditure to date: ₹1689 Cr (67.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618700. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Renigunta - Poyya - Naidupeta km 124.60 to km 183.4 of NH 71 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.