Original Cost
₹1863 Cr
Baseline estimate
Revised Cost
₹2510 Cr
Latest approved cost
Expenditure
₹1490 Cr
Spent to date
Utilization
59.4%
Of revised budget
Cost Status
+34.7%
+₹647 Cr increase
Remaining
₹1020 Cr
Budget left
Spent
₹1490 Cr
Remaining
₹1020 Cr
Total
₹2510 Cr
Original Cost
₹1863 Cr
Revised Cost
₹2510 Cr
Increase
+₹647 Cr
Escalation
+34.7%
Project Approved
Construction / Implementation
Original End Date
31/01/2024
Revised Completion
15/09/2026
Completed
Cost has increased by ₹647 Cr (34.7%) from the original estimate of ₹1863 Cr.
Expenditure stands at ₹1490 Cr, which is 59.4% of the revised project cost.
Remaining budget: ₹1020 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.