Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 Lane with Paved Shoulder of NH 965DD from Lonand Shirval-Bhor Mandangad-Pchral Section ShindewadiPhata to Varandah Ghat Dist Border from Km 33/550 to 92/550 in the state of Maharashtra on EPC mode.
Original Cost
₹723 Cr
Baseline estimate
Revised Cost
₹723 Cr
Latest approved cost
Expenditure
₹218 Cr
Spent to date
Utilization
30.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹505 Cr
Budget left
Budget Utilization
30.1%Spent
₹218 Cr
Remaining
₹505 Cr
Total
₹723 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/07/2026
Revised Completion
11/02/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹723 Cr — no cost escalation recorded.
Expenditure stands at ₹218 Cr, which is 30.1% of the revised project cost.
Remaining budget: ₹505 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 Lane with Paved Shoulder of NH 965DD from Lonand Shirval-Bhor Mandangad-Pchral Section ShindewadiPhata to Varandah Ghat Dist Border from Km 33/550 to 92/550 in the state of Maharashtra on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹723.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 L"?
- Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 Lane with Paved Shoulder of NH 965DD from Lonand Shirval-Bhor Mandangad-Pchral Section ShindewadiPhata to Varandah Ghat Dist Border from Km 33/550 to 92/550 in the state of Maharashtra on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹723 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹723 Cr has not been significantly revised. Expenditure: ₹218 Cr (30.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation, Upgradation & Widening of existing Highway t is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618199. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation, Upgradation & Widening of existing Highway t is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.