Roads & HighwaysIPM · Central Project#618199

Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 Lane with Paved Shoulder of NH 965DD from Lonand Shirval-Bhor Mandangad-Pchral Section ShindewadiPhata to Varandah Ghat Dist Border from Km 33/550 to 92/550 in the state of Maharashtra on EPC mode.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹723 CrUtilization: 30.1%

Original Cost

₹723 Cr

Baseline estimate

On budget

Revised Cost

₹723 Cr

Latest approved cost

Expenditure

₹218 Cr

Spent to date

Utilization

30.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹505 Cr

Budget left

Budget Utilization

30.1%
0%25%50%75%100%

Spent

₹218 Cr

Remaining

₹505 Cr

Total

₹723 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/07/2026

Revised Completion

11/02/2027

Completed

Project Details

Project Code618199
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹723 Cr
Revised Cost₹723 Cr
Expenditure₹218 Cr
Original End Date31/07/2026
Revised Date11/02/2027

Project Intelligence

Project is within original budget of ₹723 Cr — no cost escalation recorded.

Expenditure stands at ₹218 Cr, which is 30.1% of the revised project cost.

Remaining budget: ₹505 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 Lane with Paved Shoulder of NH 965DD from Lonand Shirval-Bhor Mandangad-Pchral Section ShindewadiPhata to Varandah Ghat Dist Border from Km 33/550 to 92/550 in the state of Maharashtra on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹723.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 L"?
Rehabilitation, Upgradation & Widening of existing Highway to Rigid Pavement 2 Lane with Paved Shoulder of NH 965DD from Lonand Shirval-Bhor Mandangad-Pchral Section ShindewadiPhata to Varandah Ghat Dist Border from Km 33/550 to 92/550 in the state of Maharashtra on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹723 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹723 Cr has not been significantly revised. Expenditure: ₹218 Cr (30.1% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation, Upgradation & Widening of existing Highway t is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618199. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation, Upgradation & Widening of existing Highway t is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.