Roads & HighwaysIPM · Central Project +3.2% overrun#618239

Rehabilitation & Upgradation of NH214 New NH-216 from Km 34/230 to Km 84/550 Losari to Machavaram Section to two lane with paved shoulder in the state of Andhrapradesh under NHDP-IV through Engineering, Procurement& Construction EPC mode.

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹459 CrUtilization: 93.9%Overrun: +₹14 Cr

Original Cost

₹445 Cr

Baseline estimate

+3% overrun

Revised Cost

₹459 Cr

Latest approved cost

Expenditure

₹431 Cr

Spent to date

Utilization

93.9%

Of revised budget

Escalated

Cost Status

+3.2%

+₹14 Cr increase

Remaining

₹28 Cr

Budget left

Budget Utilization

93.9%
0%25%50%75%100%

Spent

₹431 Cr

Remaining

₹28 Cr

Total

₹459 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹445 Cr

Revised Cost

₹459 Cr

Increase

+₹14 Cr

Escalation

+3.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/09/2018

Revised Completion

31/07/2025

Completed

Project Details

Project Code618239
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹445 Cr
Revised Cost₹459 Cr
Expenditure₹431 Cr
Original End Date07/09/2018
Revised Date31/07/2025

Project Intelligence

Cost has increased by ₹14 Cr (3.2%) from the original estimate of ₹445 Cr.

Expenditure stands at ₹431 Cr, which is 93.9% of the revised project cost.

Remaining budget: ₹28 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation & Upgradation of NH214 New NH-216 from Km 34/230 to Km 84/550 Losari to Machavaram Section to two lane with paved shoulder in the state of Andhrapradesh under NHDP-IV through Engineering, Procurement& Construction EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹445.00 Cr, later revised to ₹459.37 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation & Upgradation of NH214 New NH-216 from Km 34/230 to Km 84/550"?
Rehabilitation & Upgradation of NH214 New NH-216 from Km 34/230 to Km 84/550 Losari to Machavaram Section to two lane with paved shoulder in the state of Andhrapradesh under NHDP-IV through Engineering, Procurement& Construction EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹445 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹445 Cr and has been revised to ₹459 Cr — a cost overrun of +3.2%. Expenditure to date: ₹431 Cr (93.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation & Upgradation of NH214 New NH-216 from Km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618239. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation & Upgradation of NH214 New NH-216 from Km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.