Original Cost
₹386 Cr
Baseline estimate
Revised Cost
₹386 Cr
Latest approved cost
Expenditure
₹164 Cr
Spent to date
Utilization
42.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹222 Cr
Budget left
Spent
₹164 Cr
Remaining
₹222 Cr
Total
₹386 Cr
Project Approved
Construction / Implementation
Original End Date
03/02/2025
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹386 Cr — no cost escalation recorded.
Expenditure stands at ₹164 Cr, which is 42.6% of the revised project cost.
Remaining budget: ₹222 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.