Roads & HighwaysIPM · Central Project#618450

Rehabilitation & Upgradation of existing road to 2-lane with paved shoulder including geometric improvement of section from start of Rabangla km33.600 to km58.840 under SARDP-NE Phase A Pkg- IV

Ministry of Road Transport & HighwaysSikkim
Revised Cost: ₹293 CrUtilization: 87.5%

Original Cost

₹293 Cr

Baseline estimate

On budget

Revised Cost

₹293 Cr

Latest approved cost

Expenditure

₹257 Cr

Spent to date

Utilization

87.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹36 Cr

Budget left

Budget Utilization

87.5%
0%25%50%75%100%

Spent

₹257 Cr

Remaining

₹36 Cr

Total

₹293 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/05/2022

Revised Completion

30/12/2026

Completed

Project Details

Project Code618450
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateSikkim
Data Month2026-08

Financial Summary

Original Cost₹293 Cr
Revised Cost₹293 Cr
Expenditure₹257 Cr
Original End Date01/05/2022
Revised Date30/12/2026

Project Intelligence

Project is within original budget of ₹293 Cr — no cost escalation recorded.

Expenditure stands at ₹257 Cr, which is 87.5% of the revised project cost.

Remaining budget: ₹36 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation & Upgradation of existing road to 2-lane with paved shoulder including geometric improvement of section from start of Rabangla km33.600 to km58.840 under SARDP-NE Phase A Pkg- IV is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹293.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation & Upgradation of existing road to 2-lane with paved shoulder incl"?
Rehabilitation & Upgradation of existing road to 2-lane with paved shoulder including geometric improvement of section from start of Rabangla km33.600 to km58.840 under SARDP-NE Phase A Pkg- IV is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Sikkim. Original cost: ₹293 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹293 Cr has not been significantly revised. Expenditure: ₹257 Cr (87.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation & Upgradation of existing road to 2-lane with is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618450. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation & Upgradation of existing road to 2-lane with is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.