Roads & HighwaysIPM · Central Project#618089

Rehabilitation & Up-gradation of Mudkhed to Nanded section from Km. 372000 to Km 388400 of NH 161A i.e. Nanded-Bhokar-Himayatnagar-Kinwat-Mahur-Arani Road Design chainage from Km 372000 Mudkhed to Km 387650 Nanded of NH 161A Length 15.65 Km to 2/4Lane with paved shoulders configuration in the State of Maharashtra on EPC mode.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹207 CrUtilization: 3.8%

Original Cost

₹207 Cr

Baseline estimate

On budget

Revised Cost

₹207 Cr

Latest approved cost

Expenditure

₹8 Cr

Spent to date

Utilization

3.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹199 Cr

Budget left

Budget Utilization

3.8%
0%25%50%75%100%

Spent

₹8 Cr

Remaining

₹199 Cr

Total

₹207 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/04/2025

Revised Completion

30/10/2026

Completed

Project Details

Project Code618089
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹207 Cr
Revised Cost₹207 Cr
Expenditure₹8 Cr
Original End Date02/04/2025
Revised Date30/10/2026

Project Intelligence

Project is within original budget of ₹207 Cr — no cost escalation recorded.

Expenditure stands at ₹8 Cr, which is 3.8% of the revised project cost.

Remaining budget: ₹199 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation & Up-gradation of Mudkhed to Nanded section from Km. 372000 to Km 388400 of NH 161A i.e. Nanded-Bhokar-Himayatnagar-Kinwat-Mahur-Arani Road Design chainage from Km 372000 Mudkhed to Km 387650 Nanded of NH 161A Length 15.65 Km to 2/4Lane with paved shoulders configuration in the State of Maharashtra on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹207.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation & Up-gradation of Mudkhed to Nanded section from Km. 372000 to Km"?
Rehabilitation & Up-gradation of Mudkhed to Nanded section from Km. 372000 to Km 388400 of NH 161A i.e. Nanded-Bhokar-Himayatnagar-Kinwat-Mahur-Arani Road Design chainage from Km 372000 Mudkhed to Km 387650 Nanded of NH 161A Length 15.65 Km to 2/4Lane with paved shoulders configuration in the State of Maharashtra on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹207 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹207 Cr has not been significantly revised. Expenditure: ₹8 Cr (3.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation & Up-gradation of Mudkhed to Nanded section f is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618089. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation & Up-gradation of Mudkhed to Nanded section f is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.