Roads & HighwaysIPM · Central Project#618174

Rehabilitation and Upgradation to two lane with paved shoulder configuration of NH-752G from Sakri to Pimpalner Section Design Ch km 0000 to Ch km 21411 in the state of Maharashtra on EPC Mode. Length 21.411 km.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹227 CrUtilization: 62.8%

Original Cost

₹227 Cr

Baseline estimate

On budget

Revised Cost

₹227 Cr

Latest approved cost

Expenditure

₹143 Cr

Spent to date

Utilization

62.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹84 Cr

Budget left

Budget Utilization

62.8%
0%25%50%75%100%

Spent

₹143 Cr

Remaining

₹84 Cr

Total

₹227 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/10/2026

Revised Completion

21/10/2026

Completed

Project Details

Project Code618174
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹227 Cr
Revised Cost₹227 Cr
Expenditure₹143 Cr
Original End Date20/10/2026
Revised Date21/10/2026

Project Intelligence

Project is within original budget of ₹227 Cr — no cost escalation recorded.

Expenditure stands at ₹143 Cr, which is 62.8% of the revised project cost.

Remaining budget: ₹84 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and Upgradation to two lane with paved shoulder configuration of NH-752G from Sakri to Pimpalner Section Design Ch km 0000 to Ch km 21411 in the state of Maharashtra on EPC Mode. Length 21.411 km. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹227.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and Upgradation to two lane with paved shoulder configuration of "?
Rehabilitation and Upgradation to two lane with paved shoulder configuration of NH-752G from Sakri to Pimpalner Section Design Ch km 0000 to Ch km 21411 in the state of Maharashtra on EPC Mode. Length 21.411 km. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹227 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹227 Cr has not been significantly revised. Expenditure: ₹143 Cr (62.8% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and Upgradation to two lane with paved should is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618174. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation to two lane with paved should is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.