Roads & HighwaysIPM · Central Project +11.4% overrun#618878

Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to Rajol from Km 51.000 to Km 72.000 of NH-154 Package-IIA

Ministry of Road Transport & HighwaysHimachal Pradesh
Revised Cost: ₹777 CrUtilization: 64.0%Overrun: +₹80 Cr

Original Cost

₹697 Cr

Baseline estimate

+11% overrun

Revised Cost

₹777 Cr

Latest approved cost

Expenditure

₹497 Cr

Spent to date

Utilization

64.0%

Of revised budget

Escalated

Cost Status

+11.4%

+₹80 Cr increase

Remaining

₹280 Cr

Budget left

Budget Utilization

64.0%
0%25%50%75%100%

Spent

₹497 Cr

Remaining

₹280 Cr

Total

₹777 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹697 Cr

Revised Cost

₹777 Cr

Increase

+₹80 Cr

Escalation

+11.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/09/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code618878
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹697 Cr
Revised Cost₹777 Cr
Expenditure₹497 Cr
Original End Date26/09/2025
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹80 Cr (11.4%) from the original estimate of ₹697 Cr.

Expenditure stands at ₹497 Cr, which is 64.0% of the revised project cost.

Remaining budget: ₹280 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to Rajol from Km 51.000 to Km 72.000 of NH-154 Package-IIA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹697.00 Cr, later revised to ₹776.59 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to "?
Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to Rajol from Km 51.000 to Km 72.000 of NH-154 Package-IIA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹697 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹697 Cr and has been revised to ₹777 Cr — a cost overrun of +11.4%. Expenditure to date: ₹497 Cr (64.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and Upgradation to 4L configuration & Strengt is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618878. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation to 4L configuration & Strengt is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.