Original Cost
₹697 Cr
Baseline estimate
Revised Cost
₹777 Cr
Latest approved cost
Expenditure
₹318 Cr
Spent to date
Utilization
41.0%
Of revised budget
Cost Status
+11.4%
+₹80 Cr increase
Remaining
₹458 Cr
Budget left
Spent
₹318 Cr
Remaining
₹458 Cr
Total
₹777 Cr
Original Cost
₹697 Cr
Revised Cost
₹777 Cr
Increase
+₹80 Cr
Escalation
+11.4%
Project Approved
Construction / Implementation
Original End Date
26/09/2025
Revised Completion
30/06/2026
Completed
Cost has increased by ₹80 Cr (11.4%) from the original estimate of ₹697 Cr.
Expenditure stands at ₹318 Cr, which is 41.0% of the revised project cost.
Remaining budget: ₹458 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.