Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to Rajol from Km 51.000 to Km 72.000 of NH-154 Package-IIA
Original Cost
₹697 Cr
Baseline estimate
Revised Cost
₹777 Cr
Latest approved cost
Expenditure
₹497 Cr
Spent to date
Utilization
64.0%
Of revised budget
Cost Status
+11.4%
+₹80 Cr increase
Remaining
₹280 Cr
Budget left
Budget Utilization
64.0%Spent
₹497 Cr
Remaining
₹280 Cr
Total
₹777 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹697 Cr
Revised Cost
₹777 Cr
Increase
+₹80 Cr
Escalation
+11.4%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/09/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹80 Cr (11.4%) from the original estimate of ₹697 Cr.
Expenditure stands at ₹497 Cr, which is 64.0% of the revised project cost.
Remaining budget: ₹280 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to Rajol from Km 51.000 to Km 72.000 of NH-154 Package-IIA is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹697.00 Cr, later revised to ₹776.59 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to "?
- Rehabilitation and Upgradation to 4L configuration & Strengthening of Sihuni to Rajol from Km 51.000 to Km 72.000 of NH-154 Package-IIA is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹697 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹697 Cr and has been revised to ₹777 Cr — a cost overrun of +11.4%. Expenditure to date: ₹497 Cr (64.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgradation to 4L configuration & Strengt is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618878. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation to 4L configuration & Strengt is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.