Rehabilitation and Upgradation to 2-lane/Intermediate lane configuration of Ashyari-Shri Kyari Section km 50.000 to km 75.000 of NH-707 in the state of Himachal Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode.
Original Cost
₹346 Cr
Baseline estimate
Revised Cost
₹360 Cr
Latest approved cost
Expenditure
₹147 Cr
Spent to date
Utilization
40.8%
Of revised budget
Cost Status
+3.9%
+₹14 Cr increase
Remaining
₹213 Cr
Budget left
Budget Utilization
40.8%Spent
₹147 Cr
Remaining
₹213 Cr
Total
₹360 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹346 Cr
Revised Cost
₹360 Cr
Increase
+₹14 Cr
Escalation
+3.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/09/2023
Revised Completion
02/11/2024
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹14 Cr (3.9%) from the original estimate of ₹346 Cr.
Expenditure stands at ₹147 Cr, which is 40.8% of the revised project cost.
Remaining budget: ₹213 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgradation to 2-lane/Intermediate lane configuration of Ashyari-Shri Kyari Section km 50.000 to km 75.000 of NH-707 in the state of Himachal Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹346.00 Cr, later revised to ₹359.56 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgradation to 2-lane/Intermediate lane configuration of Ashy"?
- Rehabilitation and Upgradation to 2-lane/Intermediate lane configuration of Ashyari-Shri Kyari Section km 50.000 to km 75.000 of NH-707 in the state of Himachal Pradesh under Green National Highways Corridor Project GNHCP with the loan assistance of World Bank on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹346 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹346 Cr and has been revised to ₹360 Cr — a cost overrun of +3.9%. Expenditure to date: ₹147 Cr (40.8% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgradation to 2-lane/Intermediate lane c is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618050. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation to 2-lane/Intermediate lane c is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.