Original Cost
₹346 Cr
Baseline estimate
Revised Cost
₹360 Cr
Latest approved cost
Expenditure
₹147 Cr
Spent to date
Utilization
40.8%
Of revised budget
Cost Status
+3.9%
+₹14 Cr increase
Remaining
₹213 Cr
Budget left
Spent
₹147 Cr
Remaining
₹213 Cr
Total
₹360 Cr
Original Cost
₹346 Cr
Revised Cost
₹360 Cr
Increase
+₹14 Cr
Escalation
+3.9%
Project Approved
Construction / Implementation
Original End Date
23/09/2023
Revised Completion
02/11/2024
Completed
Cost has increased by ₹14 Cr (3.9%) from the original estimate of ₹346 Cr.
Expenditure stands at ₹147 Cr, which is 40.8% of the revised project cost.
Remaining budget: ₹213 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.