Roads & HighwaysIPM · Central Project#618226

Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 30.053 to Km 49.150 design chainage Km 30.000 to Km 46.450 including Kandi Tunnel under 31 BRTF on Akhnoor-Poonch Road NH-144A Under Project Sampark in the UT of Jammu & Kashmir EPC modePackage-I Job no NH-144A-J&K-2020-21-83.

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹272 CrUtilization: 73.7%

Original Cost

₹272 Cr

Baseline estimate

On budget

Revised Cost

₹272 Cr

Latest approved cost

Expenditure

₹200 Cr

Spent to date

Utilization

73.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹72 Cr

Budget left

Budget Utilization

73.7%
0%25%50%75%100%

Spent

₹200 Cr

Remaining

₹72 Cr

Total

₹272 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/11/2024

Revised Completion

31/12/2026

Completed

Project Details

Project Code618226
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹272 Cr
Revised Cost₹272 Cr
Expenditure₹200 Cr
Original End Date28/11/2024
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹272 Cr — no cost escalation recorded.

Expenditure stands at ₹200 Cr, which is 73.7% of the revised project cost.

Remaining budget: ₹72 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 30.053 to Km 49.150 design chainage Km 30.000 to Km 46.450 including Kandi Tunnel under 31 BRTF on Akhnoor-Poonch Road NH-144A Under Project Sampark in the UT of Jammu & Kashmir EPC modePackage-I Job no NH-144A-J&K-2020-21-83. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹272.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and upgradation to 2 lane with paved shoulder from existing chain"?
Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 30.053 to Km 49.150 design chainage Km 30.000 to Km 46.450 including Kandi Tunnel under 31 BRTF on Akhnoor-Poonch Road NH-144A Under Project Sampark in the UT of Jammu & Kashmir EPC modePackage-I Job no NH-144A-J&K-2020-21-83. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹272 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹272 Cr has not been significantly revised. Expenditure: ₹200 Cr (73.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and upgradation to 2 lane with paved shoulder is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618226. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and upgradation to 2 lane with paved shoulder is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.