Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 30.053 to Km 49.150 design chainage Km 30.000 to Km 46.450 including Kandi Tunnel under 31 BRTF on Akhnoor-Poonch Road NH-144A Under Project Sampark in the UT of Jammu & Kashmir EPC modePackage-I Job no NH-144A-J&K-2020-21-83.
Original Cost
₹272 Cr
Baseline estimate
Revised Cost
₹272 Cr
Latest approved cost
Expenditure
₹200 Cr
Spent to date
Utilization
73.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹72 Cr
Budget left
Budget Utilization
73.7%Spent
₹200 Cr
Remaining
₹72 Cr
Total
₹272 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
28/11/2024
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹272 Cr — no cost escalation recorded.
Expenditure stands at ₹200 Cr, which is 73.7% of the revised project cost.
Remaining budget: ₹72 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 30.053 to Km 49.150 design chainage Km 30.000 to Km 46.450 including Kandi Tunnel under 31 BRTF on Akhnoor-Poonch Road NH-144A Under Project Sampark in the UT of Jammu & Kashmir EPC modePackage-I Job no NH-144A-J&K-2020-21-83. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹272.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and upgradation to 2 lane with paved shoulder from existing chain"?
- Rehabilitation and upgradation to 2 lane with paved shoulder from existing chainage Km 30.053 to Km 49.150 design chainage Km 30.000 to Km 46.450 including Kandi Tunnel under 31 BRTF on Akhnoor-Poonch Road NH-144A Under Project Sampark in the UT of Jammu & Kashmir EPC modePackage-I Job no NH-144A-J&K-2020-21-83. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹272 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹272 Cr has not been significantly revised. Expenditure: ₹200 Cr (73.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and upgradation to 2 lane with paved shoulder is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618226. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and upgradation to 2 lane with paved shoulder is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.