Original Cost
₹325 Cr
Baseline estimate
Revised Cost
₹340 Cr
Latest approved cost
Expenditure
₹0 Cr
Spent to date
Utilization
0.0%
Of revised budget
Cost Status
+4.7%
+₹15 Cr increase
Remaining
₹340 Cr
Budget left
Spent
₹0 Cr
Remaining
₹340 Cr
Total
₹340 Cr
Original Cost
₹325 Cr
Revised Cost
₹340 Cr
Increase
+₹15 Cr
Escalation
+4.7%
Project Approved
Construction / Implementation
Original End Date
23/11/2024
Revised Completion
30/04/2026
Completed
Cost has increased by ₹15 Cr (4.7%) from the original estimate of ₹325 Cr.
Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.
Remaining budget: ₹340 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.