Rehabilitation and Upgradation of road Rishikesh Dharasu Old NH-94 with 2-lane with paved shoulder from km 76.000 to km 110.000 Design Chainage from km 74.733 to km 107.347 32.614 km including construction of Kamand re-alignment from existing Chainage Km 105.200 to Km 108.600 design chainage Km 103.436 to Km 105.949 - total length 2513 mtrs and land slide treatment work between design chainage Km 73.800 to Km 74.00 200m on EPC mode under improvement to NH connectivity to Chardham in
Original Cost
₹274 Cr
Baseline estimate
Revised Cost
₹274 Cr
Latest approved cost
Expenditure
₹228 Cr
Spent to date
Utilization
83.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹46 Cr
Budget left
Budget Utilization
83.2%Spent
₹228 Cr
Remaining
₹46 Cr
Total
₹274 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
05/01/2021
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹274 Cr — no cost escalation recorded.
Expenditure stands at ₹228 Cr, which is 83.2% of the revised project cost.
Remaining budget: ₹46 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Upgradation of road Rishikesh Dharasu Old NH-94 with 2-lane with paved shoulder from km 76.000 to km 110.000 Design Chainage from km 74.733 to km 107.347 32.614 km including construction of Kamand re-alignment from existing Chainage Km 105.200 to Km 108.600 design chainage Km 103.436 to Km 105.949 - total length 2513 mtrs and land slide treatment work between design chainage Km 73.800 to Km 74.00 200m on EPC mode under improvement to NH connectivity to Chardham in is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹274.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Upgradation of road Rishikesh Dharasu Old NH-94 with 2-lane "?
- Rehabilitation and Upgradation of road Rishikesh Dharasu Old NH-94 with 2-lane with paved shoulder from km 76.000 to km 110.000 Design Chainage from km 74.733 to km 107.347 32.614 km including construction of Kamand re-alignment from existing Chainage Km 105.200 to Km 108.600 design chainage Km 103.436 to Km 105.949 - total length 2513 mtrs and land slide treatment work between design chainage Km 73.800 to Km 74.00 200m on EPC mode under improvement to NH connectivity to Chardham in is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹274 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹274 Cr has not been significantly revised. Expenditure: ₹228 Cr (83.2% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and Upgradation of road Rishikesh Dharasu Ol is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618213. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Upgradation of road Rishikesh Dharasu Ol is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.