Original Cost
₹228 Cr
Baseline estimate
Revised Cost
₹228 Cr
Latest approved cost
Expenditure
₹44 Cr
Spent to date
Utilization
19.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹184 Cr
Budget left
Spent
₹44 Cr
Remaining
₹184 Cr
Total
₹228 Cr
Project Approved
Construction / Implementation
Original End Date
27/03/2020
Revised Completion
07/10/2025
Completed
Project is within original budget of ₹228 Cr — no cost escalation recorded.
Expenditure stands at ₹44 Cr, which is 19.5% of the revised project cost.
Remaining budget: ₹184 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.