Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of Mahud Sangola road NH 965 G 159400 to 161900and 162400 to 183960 Design Chainage from km. 32/300 to km. 34/800 and km. 35/800 to km. 56/860 Rigid Pavement on EPC mode in the State of Maharashtra.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹254 CrUtilization: 39.0%

Original Cost

₹254 Cr

Baseline estimate

On budget

Revised Cost

₹254 Cr

Latest approved cost

Expenditure

₹99 Cr

Spent to date

Utilization

39.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹155 Cr

Budget left

Budget Utilization

39.0%
0%25%50%75%100%

Spent

₹99 Cr

Remaining

₹155 Cr

Total

₹254 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/05/2025

Revised Completion

31/08/2026

Completed

Project Details

Project Code618188
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-07

Financial Summary

Original Cost₹254 Cr
Revised Cost₹254 Cr
Expenditure₹99 Cr
Original End Date22/05/2025
Revised Date31/08/2026

Project Intelligence

Project is within original budget of ₹254 Cr — no cost escalation recorded.

Expenditure stands at ₹99 Cr, which is 39.0% of the revised project cost.

Remaining budget: ₹155 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of Mahud Sangola road NH 965 G 159400 to 161900and 162400 to 183960 Design Chainage from km. 32/300 to km. 34/800 and km. 35/800 to km. 56/860 Rigid Pavement on EPC mode in the State of Maharashtra. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹254.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of M"?
Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of Mahud Sangola road NH 965 G 159400 to 161900and 162400 to 183960 Design Chainage from km. 32/300 to km. 34/800 and km. 35/800 to km. 56/860 Rigid Pavement on EPC mode in the State of Maharashtra. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹254 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹254 Cr has not been significantly revised. Expenditure: ₹99 Cr (39.0% of cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Rehabilitation and Up-gradation to 2 lane with paved shoulde is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618188. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Up-gradation to 2 lane with paved shoulde is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.