Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of Mahud Sangola road NH 965 G 159400 to 161900and 162400 to 183960 Design Chainage from km. 32/300 to km. 34/800 and km. 35/800 to km. 56/860 Rigid Pavement on EPC mode in the State of Maharashtra.
Original Cost
₹254 Cr
Baseline estimate
Revised Cost
₹254 Cr
Latest approved cost
Expenditure
₹99 Cr
Spent to date
Utilization
39.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹155 Cr
Budget left
Budget Utilization
39.0%Spent
₹99 Cr
Remaining
₹155 Cr
Total
₹254 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/05/2025
Revised Completion
31/08/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹254 Cr — no cost escalation recorded.
Expenditure stands at ₹99 Cr, which is 39.0% of the revised project cost.
Remaining budget: ₹155 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of Mahud Sangola road NH 965 G 159400 to 161900and 162400 to 183960 Design Chainage from km. 32/300 to km. 34/800 and km. 35/800 to km. 56/860 Rigid Pavement on EPC mode in the State of Maharashtra. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹254.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of M"?
- Rehabilitation and Up-gradation to 2 lane with paved shoulder configuration of Mahud Sangola road NH 965 G 159400 to 161900and 162400 to 183960 Design Chainage from km. 32/300 to km. 34/800 and km. 35/800 to km. 56/860 Rigid Pavement on EPC mode in the State of Maharashtra. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹254 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹254 Cr has not been significantly revised. Expenditure: ₹99 Cr (39.0% of cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Rehabilitation and Up-gradation to 2 lane with paved shoulde is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618188. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Up-gradation to 2 lane with paved shoulde is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.