Roads & HighwaysIPM · Central Project#618385

Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total lengh 11.210 km of Kailashahar-Kurti Bridge section on NH-208A to 2-lane with paved shoulder on EPC basis under NHO Package-III- Balance Work

Ministry of Road Transport & HighwaysTripura
Revised Cost: ₹174 CrUtilization: 38.6%

Original Cost

₹174 Cr

Baseline estimate

On budget

Revised Cost

₹174 Cr

Latest approved cost

Expenditure

₹67 Cr

Spent to date

Utilization

38.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹107 Cr

Budget left

Budget Utilization

38.6%
0%25%50%75%100%

Spent

₹67 Cr

Remaining

₹107 Cr

Total

₹174 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/03/2026

Revised Completion

02/03/2026

Completed

Project Details

Project Code618385
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTripura
Data Month2026-08

Financial Summary

Original Cost₹174 Cr
Revised Cost₹174 Cr
Expenditure₹67 Cr
Original End Date02/03/2026
Revised Date02/03/2026

Project Intelligence

Project is within original budget of ₹174 Cr — no cost escalation recorded.

Expenditure stands at ₹67 Cr, which is 38.6% of the revised project cost.

Remaining budget: ₹107 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total lengh 11.210 km of Kailashahar-Kurti Bridge section on NH-208A to 2-lane with paved shoulder on EPC basis under NHO Package-III- Balance Work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹174.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total"?
Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total lengh 11.210 km of Kailashahar-Kurti Bridge section on NH-208A to 2-lane with paved shoulder on EPC basis under NHO Package-III- Balance Work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tripura. Original cost: ₹174 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹174 Cr has not been significantly revised. Expenditure: ₹67 Cr (38.6% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and up-gradation of road from design km 25.25 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618385. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and up-gradation of road from design km 25.25 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.