Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total lengh 11.210 km of Kailashahar-Kurti Bridge section on NH-208A to 2-lane with paved shoulder on EPC basis under NHO Package-III- Balance Work
Original Cost
₹174 Cr
Baseline estimate
Revised Cost
₹174 Cr
Latest approved cost
Expenditure
₹67 Cr
Spent to date
Utilization
38.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹107 Cr
Budget left
Budget Utilization
38.6%Spent
₹67 Cr
Remaining
₹107 Cr
Total
₹174 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
02/03/2026
Revised Completion
02/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹174 Cr — no cost escalation recorded.
Expenditure stands at ₹67 Cr, which is 38.6% of the revised project cost.
Remaining budget: ₹107 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total lengh 11.210 km of Kailashahar-Kurti Bridge section on NH-208A to 2-lane with paved shoulder on EPC basis under NHO Package-III- Balance Work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹174.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total"?
- Rehabilitation and up-gradation of road from design km 25.250 to km 36.460 Total lengh 11.210 km of Kailashahar-Kurti Bridge section on NH-208A to 2-lane with paved shoulder on EPC basis under NHO Package-III- Balance Work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tripura. Original cost: ₹174 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹174 Cr has not been significantly revised. Expenditure: ₹67 Cr (38.6% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and up-gradation of road from design km 25.25 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618385. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and up-gradation of road from design km 25.25 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.