Rehabilitation and Up-gradation of i. Deogaon phata to Digras phata Ch. 0/000 to 15/000 & Selu to Borgavhan Ch 20/900 to 35/800 [Length 29.9km] ii. Injegaon Dhamoni to Pohner Phata Ch.58/200 to Ch. 83/700 [Length25.5 km] and iii. Pohner phata to Pathri Design Ch. 42/700 to 58/200 [Length 15.5 km] sections of NH-548B to Two lane with paved shoulder configuartion in the state of Maharashtra on EPC mode Total project length 70.9 Km.
Original Cost
₹762 Cr
Baseline estimate
Revised Cost
₹762 Cr
Latest approved cost
Expenditure
₹97 Cr
Spent to date
Utilization
12.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹665 Cr
Budget left
Budget Utilization
12.7%Spent
₹97 Cr
Remaining
₹665 Cr
Total
₹762 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/05/2027
Revised Completion
08/05/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹762 Cr — no cost escalation recorded.
Expenditure stands at ₹97 Cr, which is 12.7% of the revised project cost.
Remaining budget: ₹665 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Up-gradation of i. Deogaon phata to Digras phata Ch. 0/000 to 15/000 & Selu to Borgavhan Ch 20/900 to 35/800 [Length 29.9km] ii. Injegaon Dhamoni to Pohner Phata Ch.58/200 to Ch. 83/700 [Length25.5 km] and iii. Pohner phata to Pathri Design Ch. 42/700 to 58/200 [Length 15.5 km] sections of NH-548B to Two lane with paved shoulder configuartion in the state of Maharashtra on EPC mode Total project length 70.9 Km. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹762.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Up-gradation of i. Deogaon phata to Digras phata Ch. 0/000 to"?
- Rehabilitation and Up-gradation of i. Deogaon phata to Digras phata Ch. 0/000 to 15/000 & Selu to Borgavhan Ch 20/900 to 35/800 [Length 29.9km] ii. Injegaon Dhamoni to Pohner Phata Ch.58/200 to Ch. 83/700 [Length25.5 km] and iii. Pohner phata to Pathri Design Ch. 42/700 to 58/200 [Length 15.5 km] sections of NH-548B to Two lane with paved shoulder configuartion in the state of Maharashtra on EPC mode Total project length 70.9 Km. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹762 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹762 Cr has not been significantly revised. Expenditure: ₹97 Cr (12.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Rehabilitation and Up-gradation of i. Deogaon phata to Digra is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618150. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Up-gradation of i. Deogaon phata to Digra is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.