Roads & HighwaysIPM · Central Project +18.6% overrun#618888

Rehabilitation and Up-gradation of existing road to 2L PS from End of Hamirpur Bypass near Chilbahal to Bhangbar section from Km. 138.295 to Km.175.270 of NH-88 Pkg-IV

Ministry of Road Transport & HighwaysHimachal Pradesh
Revised Cost: ₹1359 CrUtilization: 72.7%Overrun: +₹213 Cr

Original Cost

₹1146 Cr

Baseline estimate

+19% overrun

Revised Cost

₹1359 Cr

Latest approved cost

Expenditure

₹988 Cr

Spent to date

Utilization

72.7%

Of revised budget

Escalated

Cost Status

+18.6%

+₹213 Cr increase

Remaining

₹371 Cr

Budget left

Budget Utilization

72.7%
0%25%50%75%100%

Spent

₹988 Cr

Remaining

₹371 Cr

Total

₹1359 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1146 Cr

Revised Cost

₹1359 Cr

Increase

+₹213 Cr

Escalation

+18.6%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/04/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code618888
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1146 Cr
Revised Cost₹1359 Cr
Expenditure₹988 Cr
Original End Date27/04/2025
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹213 Cr (18.6%) from the original estimate of ₹1146 Cr.

Expenditure stands at ₹988 Cr, which is 72.7% of the revised project cost.

Remaining budget: ₹371 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and Up-gradation of existing road to 2L PS from End of Hamirpur Bypass near Chilbahal to Bhangbar section from Km. 138.295 to Km.175.270 of NH-88 Pkg-IV is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1146.00 Cr, later revised to ₹1358.62 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and Up-gradation of existing road to 2L PS from End of Hamirpur B"?
Rehabilitation and Up-gradation of existing road to 2L PS from End of Hamirpur Bypass near Chilbahal to Bhangbar section from Km. 138.295 to Km.175.270 of NH-88 Pkg-IV is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹1146 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1146 Cr and has been revised to ₹1359 Cr — a cost overrun of +18.6%. Expenditure to date: ₹988 Cr (72.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and Up-gradation of existing road to 2L PS fr is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618888. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Up-gradation of existing road to 2L PS fr is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.