Original Cost
₹1146 Cr
Baseline estimate
Revised Cost
₹1359 Cr
Latest approved cost
Expenditure
₹294 Cr
Spent to date
Utilization
21.6%
Of revised budget
Cost Status
+18.6%
+₹213 Cr increase
Remaining
₹1065 Cr
Budget left
Spent
₹294 Cr
Remaining
₹1065 Cr
Total
₹1359 Cr
Original Cost
₹1146 Cr
Revised Cost
₹1359 Cr
Increase
+₹213 Cr
Escalation
+18.6%
Project Approved
Construction / Implementation
Original End Date
27/04/2025
Revised Completion
20/07/2026
Completed
Cost has increased by ₹213 Cr (18.6%) from the original estimate of ₹1146 Cr.
Expenditure stands at ₹294 Cr, which is 21.6% of the revised project cost.
Remaining budget: ₹1065 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.