Rehabilitation and Up-gradation from Km 170700 Bhadrachalam to Km 234567 Konta on NH-30 to Two lane with Paved Shoulder in the State of Andra Pradesh on EPC mode.
Original Cost
₹436 Cr
Baseline estimate
Revised Cost
₹436 Cr
Latest approved cost
Expenditure
₹221 Cr
Spent to date
Utilization
50.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹215 Cr
Budget left
Budget Utilization
50.7%Spent
₹221 Cr
Remaining
₹215 Cr
Total
₹436 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/09/2024
Revised Completion
30/04/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹436 Cr — no cost escalation recorded.
Expenditure stands at ₹221 Cr, which is 50.7% of the revised project cost.
Remaining budget: ₹215 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Rehabilitation and Up-gradation from Km 170700 Bhadrachalam to Km 234567 Konta on NH-30 to Two lane with Paved Shoulder in the State of Andra Pradesh on EPC mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹436.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rehabilitation and Up-gradation from Km 170700 Bhadrachalam to Km 234567 Konta o"?
- Rehabilitation and Up-gradation from Km 170700 Bhadrachalam to Km 234567 Konta on NH-30 to Two lane with Paved Shoulder in the State of Andra Pradesh on EPC mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹436 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹436 Cr has not been significantly revised. Expenditure: ₹221 Cr (50.7% of cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Rehabilitation and Up-gradation from Km 170700 Bhadrachalam is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617907. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Up-gradation from Km 170700 Bhadrachalam is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.