Original Cost
₹920 Cr
Baseline estimate
Revised Cost
₹950 Cr
Latest approved cost
Expenditure
₹422 Cr
Spent to date
Utilization
44.4%
Of revised budget
Cost Status
+3.3%
+₹30 Cr increase
Remaining
₹529 Cr
Budget left
Spent
₹422 Cr
Remaining
₹529 Cr
Total
₹950 Cr
Original Cost
₹920 Cr
Revised Cost
₹950 Cr
Increase
+₹30 Cr
Escalation
+3.3%
Project Approved
Construction / Implementation
Original End Date
14/12/2025
Revised Completion
31/08/2026
Completed
Cost has increased by ₹30 Cr (3.3%) from the original estimate of ₹920 Cr.
Expenditure stands at ₹422 Cr, which is 44.4% of the revised project cost.
Remaining budget: ₹529 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.