Roads & HighwaysIPM · Central Project +3.3% overrun#618821

Rehabilitation and Up gradation from 4 to 8 laning of Chandikhole Paradip Section of NH-53 Old NH 5A from Km 18.00 to Km 39.00 in the State of Odisha on HAM mode Package-2

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹950 CrUtilization: 45.8%Overrun: +₹30 Cr

Original Cost

₹920 Cr

Baseline estimate

+3% overrun

Revised Cost

₹950 Cr

Latest approved cost

Expenditure

₹435 Cr

Spent to date

Utilization

45.8%

Of revised budget

Escalated

Cost Status

+3.3%

+₹30 Cr increase

Remaining

₹515 Cr

Budget left

Budget Utilization

45.8%
0%25%50%75%100%

Spent

₹435 Cr

Remaining

₹515 Cr

Total

₹950 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹920 Cr

Revised Cost

₹950 Cr

Increase

+₹30 Cr

Escalation

+3.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/12/2025

Revised Completion

30/11/2026

Completed

Project Details

Project Code618821
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹920 Cr
Revised Cost₹950 Cr
Expenditure₹435 Cr
Original End Date14/12/2025
Revised Date30/11/2026

Project Intelligence

Cost has increased by ₹30 Cr (3.3%) from the original estimate of ₹920 Cr.

Expenditure stands at ₹435 Cr, which is 45.8% of the revised project cost.

Remaining budget: ₹515 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Rehabilitation and Up gradation from 4 to 8 laning of Chandikhole Paradip Section of NH-53 Old NH 5A from Km 18.00 to Km 39.00 in the State of Odisha on HAM mode Package-2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹920.00 Cr, later revised to ₹950.40 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rehabilitation and Up gradation from 4 to 8 laning of Chandikhole Paradip Secti"?
Rehabilitation and Up gradation from 4 to 8 laning of Chandikhole Paradip Section of NH-53 Old NH 5A from Km 18.00 to Km 39.00 in the State of Odisha on HAM mode Package-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹920 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹920 Cr and has been revised to ₹950 Cr — a cost overrun of +3.3%. Expenditure to date: ₹435 Cr (45.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Rehabilitation and Up gradation from 4 to 8 laning of Chandi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618821. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rehabilitation and Up gradation from 4 to 8 laning of Chandi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.