Roads & HighwaysIPM · Central Project +43.8% overrun#618428

Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 Km 3.100 of NH-717A with two lane paved shoulder including Major Bridge of 680 m in the State of Sikkim on EPC Mode-COS work

Ministry of Road Transport & HighwaysSikkim
Revised Cost: ₹381 CrUtilization: 18.6%Overrun: +₹116 Cr

Original Cost

₹265 Cr

Baseline estimate

+44% overrun

Revised Cost

₹381 Cr

Latest approved cost

Expenditure

₹71 Cr

Spent to date

Utilization

18.6%

Of revised budget

Escalated

Cost Status

+43.8%

+₹116 Cr increase

Remaining

₹310 Cr

Budget left

Budget Utilization

18.6%
0%25%50%75%100%

Spent

₹71 Cr

Remaining

₹310 Cr

Total

₹381 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹265 Cr

Revised Cost

₹381 Cr

Increase

+₹116 Cr

Escalation

+43.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/04/2023

Revised Completion

21/05/2026

Completed

Project Details

Project Code618428
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateSikkim
Data Month2026-08

Financial Summary

Original Cost₹265 Cr
Revised Cost₹381 Cr
Expenditure₹71 Cr
Original End Date10/04/2023
Revised Date21/05/2026

Project Intelligence

Cost has increased by ₹116 Cr (43.8%) from the original estimate of ₹265 Cr.

Expenditure stands at ₹71 Cr, which is 18.6% of the revised project cost.

Remaining budget: ₹310 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 Km 3.100 of NH-717A with two lane paved shoulder including Major Bridge of 680 m in the State of Sikkim on EPC Mode-COS work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹265.00 Cr, later revised to ₹380.94 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 "?
Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 Km 3.100 of NH-717A with two lane paved shoulder including Major Bridge of 680 m in the State of Sikkim on EPC Mode-COS work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Sikkim. Original cost: ₹265 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹265 Cr and has been revised to ₹381 Cr — a cost overrun of +43.8%. Expenditure to date: ₹71 Cr (18.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618428. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.