Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 Km 3.100 of NH-717A with two lane paved shoulder including Major Bridge of 680 m in the State of Sikkim on EPC Mode-COS work
Original Cost
₹265 Cr
Baseline estimate
Revised Cost
₹381 Cr
Latest approved cost
Expenditure
₹71 Cr
Spent to date
Utilization
18.6%
Of revised budget
Cost Status
+43.8%
+₹116 Cr increase
Remaining
₹310 Cr
Budget left
Budget Utilization
18.6%Spent
₹71 Cr
Remaining
₹310 Cr
Total
₹381 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹265 Cr
Revised Cost
₹381 Cr
Increase
+₹116 Cr
Escalation
+43.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
10/04/2023
Revised Completion
21/05/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹116 Cr (43.8%) from the original estimate of ₹265 Cr.
Expenditure stands at ₹71 Cr, which is 18.6% of the revised project cost.
Remaining budget: ₹310 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 Km 3.100 of NH-717A with two lane paved shoulder including Major Bridge of 680 m in the State of Sikkim on EPC Mode-COS work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹265.00 Cr, later revised to ₹380.94 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 "?
- Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-10 to Design Ch.2.00 Km 3.100 of NH-717A with two lane paved shoulder including Major Bridge of 680 m in the State of Sikkim on EPC Mode-COS work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Sikkim. Original cost: ₹265 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹265 Cr and has been revised to ₹381 Cr — a cost overrun of +43.8%. Expenditure to date: ₹71 Cr (18.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618428. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Realignment of NH-717A from Design Ch.0.00 Km 77.800 of NH-1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.