Original Cost
₹480 Cr
Baseline estimate
Revised Cost
₹480 Cr
Latest approved cost
Expenditure
₹21 Cr
Spent to date
Utilization
4.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹459 Cr
Budget left
Spent
₹21 Cr
Remaining
₹459 Cr
Total
₹480 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2024
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹480 Cr — no cost escalation recorded.
Expenditure stands at ₹21 Cr, which is 4.3% of the revised project cost.
Remaining budget: ₹459 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.