RailwaysIPM · Central Project +84.8% overrun#705494

Rayadurg-Tumkur via Kalyandurg 213 km

Ministry of RailwaysKarnataka
Revised Cost: ₹4612 CrUtilization: 41.3%Overrun: +₹2116 Cr

Original Cost

₹2496 Cr

Baseline estimate

+85% overrun

Revised Cost

₹4612 Cr

Latest approved cost

Expenditure

₹1907 Cr

Spent to date

Utilization

41.3%

Of revised budget

Escalated

Cost Status

+84.8%

+₹2116 Cr increase

Remaining

₹2705 Cr

Budget left

Budget Utilization

41.3%
0%25%50%75%100%

Spent

₹1907 Cr

Remaining

₹2705 Cr

Total

₹4612 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2496 Cr

Revised Cost

₹4612 Cr

Increase

+₹2116 Cr

Escalation

+84.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/09/2015

Revised Completion

29/02/2028

Completed

Project Details

Project Code705494
SectorRailways
MinistryMinistry of Railways
StateKarnataka
Data Month2026-07

Financial Summary

Original Cost₹2496 Cr
Revised Cost₹4612 Cr
Expenditure₹1907 Cr
Original End Date30/09/2015
Revised Date29/02/2028

Project Intelligence

Cost has increased by ₹2116 Cr (84.8%) from the original estimate of ₹2496 Cr.

Expenditure stands at ₹1907 Cr, which is 41.3% of the revised project cost.

Remaining budget: ₹2705 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Rayadurg-Tumkur via Kalyandurg 213 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2496.00 Cr, later revised to ₹4612.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Rayadurg-Tumkur via Kalyandurg 213 km"?
Rayadurg-Tumkur via Kalyandurg 213 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹2496 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2496 Cr and has been revised to ₹4612 Cr — a cost overrun of +84.8%. Expenditure to date: ₹1907 Cr (41.3% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
Rayadurg-Tumkur via Kalyandurg 213 km is under the Ministry of Railways in the Railways sector. Project code: 705494. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rayadurg-Tumkur via Kalyandurg 213 km is one of several Bihar projects tracked under the Railways sector on the IPM system.