Rampur Dumra-Tal-Rajendrapul - Addl bridge and doubling 14 km
Original Cost
₹2374 Cr
Baseline estimate
Revised Cost
₹2535 Cr
Latest approved cost
Expenditure
₹2028 Cr
Spent to date
Utilization
80.0%
Of revised budget
Cost Status
+6.8%
+₹161 Cr increase
Remaining
₹507 Cr
Budget left
Budget Utilization
80.0%Spent
₹2028 Cr
Remaining
₹507 Cr
Total
₹2535 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2374 Cr
Revised Cost
₹2535 Cr
Increase
+₹161 Cr
Escalation
+6.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
01/12/2024
Revised Completion
31/12/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹161 Cr (6.8%) from the original estimate of ₹2374 Cr.
Expenditure stands at ₹2028 Cr, which is 80.0% of the revised project cost.
Remaining budget: ₹507 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Rampur Dumra-Tal-Rajendrapul - Addl bridge and doubling 14 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2374.00 Cr, later revised to ₹2535.13 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Rampur Dumra-Tal-Rajendrapul - Addl bridge and doubling 14 km"?
- Rampur Dumra-Tal-Rajendrapul - Addl bridge and doubling 14 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Bihar. Original cost: ₹2374 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2374 Cr and has been revised to ₹2535 Cr — a cost overrun of +6.8%. Expenditure to date: ₹2028 Cr (80.0% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Rampur Dumra-Tal-Rajendrapul - Addl bridge and doubling 14 k is under the Ministry of Railways in the Railways sector. Project code: 706759. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Rampur Dumra-Tal-Rajendrapul - Addl bridge and doubling 14 k is one of several Bihar projects tracked under the Railways sector on the IPM system.