Original Cost
₹1402 Cr
Baseline estimate
Revised Cost
₹2510 Cr
Latest approved cost
Expenditure
₹1840 Cr
Spent to date
Utilization
73.3%
Of revised budget
Cost Status
+79.0%
+₹1108 Cr increase
Remaining
₹670 Cr
Budget left
Spent
₹1840 Cr
Remaining
₹670 Cr
Total
₹2510 Cr
Original Cost
₹1402 Cr
Revised Cost
₹2510 Cr
Increase
+₹1108 Cr
Escalation
+79.0%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/03/2026
Completed
Cost has increased by ₹1108 Cr (79.0%) from the original estimate of ₹1402 Cr.
Expenditure stands at ₹1840 Cr, which is 73.3% of the revised project cost.
Remaining budget: ₹670 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.