RailwaysIPM · Central Project +0.3% overrun#611944

Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing direct entry towards Mundra Port and Bhuj and high level platform at Gopalpur 11Kms

Ministry of RailwaysGujarat
Revised Cost: ₹152 CrUtilization: 79.0%Overrun: +₹0 Cr

Original Cost

₹152 Cr

Baseline estimate

+0% overrun

Revised Cost

₹152 Cr

Latest approved cost

Expenditure

₹120 Cr

Spent to date

Utilization

79.0%

Of revised budget

Escalated

Cost Status

+0.3%

+₹0 Cr increase

Remaining

₹32 Cr

Budget left

Budget Utilization

79.0%
0%25%50%75%100%

Spent

₹120 Cr

Remaining

₹32 Cr

Total

₹152 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹152 Cr

Revised Cost

₹152 Cr

Increase

+₹0 Cr

Escalation

+0.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2026

Revised Completion

31/01/2026

Completed

Project Details

Project Code611944
SectorRailways
MinistryMinistry of Railways
StateGujarat
Data Month2026-01

Financial Summary

Original Cost₹152 Cr
Revised Cost₹152 Cr
Expenditure₹120 Cr
Original End Date31/03/2026
Revised Date31/01/2026

Project Intelligence

Cost has increased by ₹0 Cr (0.3%) from the original estimate of ₹152 Cr.

Expenditure stands at ₹120 Cr, which is 79.0% of the revised project cost.

Remaining budget: ₹32 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing direct entry towards Mundra Port and Bhuj and high level platform at Gopalpur 11Kms is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹152.00 Cr, later revised to ₹152.44 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing "?
Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing direct entry towards Mundra Port and Bhuj and high level platform at Gopalpur 11Kms is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹152 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹152 Cr and has been revised to ₹152 Cr — a cost overrun of +0.3%. Expenditure to date: ₹120 Cr (79.0% of revised cost). Data as of 2026-01.
QWhich ministry is responsible for this project?
Quadrupling between Gandhidham Adipur with Y connection at A is under the Ministry of Railways in the Railways sector. Project code: 611944. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Quadrupling between Gandhidham Adipur with Y connection at A is one of several Bihar projects tracked under the Railways sector on the IPM system.