Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing direct entry towards Mundra Port and Bhuj and high level platform at Gopalpur 11Kms
Original Cost
₹152 Cr
Baseline estimate
Revised Cost
₹152 Cr
Latest approved cost
Expenditure
₹120 Cr
Spent to date
Utilization
79.0%
Of revised budget
Cost Status
+0.3%
+₹0 Cr increase
Remaining
₹32 Cr
Budget left
Budget Utilization
79.0%Spent
₹120 Cr
Remaining
₹32 Cr
Total
₹152 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹152 Cr
Revised Cost
₹152 Cr
Increase
+₹0 Cr
Escalation
+0.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
31/01/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹0 Cr (0.3%) from the original estimate of ₹152 Cr.
Expenditure stands at ₹120 Cr, which is 79.0% of the revised project cost.
Remaining budget: ₹32 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing direct entry towards Mundra Port and Bhuj and high level platform at Gopalpur 11Kms is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹152.00 Cr, later revised to ₹152.44 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing "?
- Quadrupling between Gandhidham Adipur with Y connection at Adipur for providing direct entry towards Mundra Port and Bhuj and high level platform at Gopalpur 11Kms is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹152 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹152 Cr and has been revised to ₹152 Cr — a cost overrun of +0.3%. Expenditure to date: ₹120 Cr (79.0% of revised cost). Data as of 2026-01.
- QWhich ministry is responsible for this project?
- Quadrupling between Gandhidham Adipur with Y connection at A is under the Ministry of Railways in the Railways sector. Project code: 611944. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Quadrupling between Gandhidham Adipur with Y connection at A is one of several Bihar projects tracked under the Railways sector on the IPM system.