Project
Original Cost
₹571 Cr
Baseline estimate
Revised Cost
₹658 Cr
Latest approved cost
Expenditure
₹448 Cr
Spent to date
Utilization
68.0%
Of revised cost
Cost Overrun
+15.3%
+₹87 Cr
Remaining
₹210 Cr
Budget left
Spent
₹448 Cr
Remaining
₹210 Cr
Total
₹658 Cr
68.0%
Utilized
Original Cost
₹571 Cr
Revised Cost
₹658 Cr
Increase
+₹87 Cr
Escalation
+15.3%
Project Approved
Construction / Implementation
Original End Date
2019-12-31
Revised Completion
2026-03-31
Completed
Cost has increased by ₹87 Cr (15.3%) from the original estimate of ₹571 Cr.
Expenditure stands at ₹448 Cr, which is 68.0% of the revised project cost.
Remaining budget: ₹210 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.