Original Cost
₹1588 Cr
Baseline estimate
Revised Cost
₹1416 Cr
Latest approved cost
Expenditure
₹449 Cr
Spent to date
Utilization
31.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹967 Cr
Budget left
Spent
₹449 Cr
Remaining
₹967 Cr
Total
₹1416 Cr
Project Approved
Construction / Implementation
Original End Date
14/11/2023
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹1588 Cr — no cost escalation recorded.
Expenditure stands at ₹449 Cr, which is 31.7% of the revised project cost.
Remaining budget: ₹967 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.