RailwaysIPM · Central Project +5.7% overrun#705385

Pirpainti - Jasidih 97 km

Ministry of RailwaysJharkhand
Revised Cost: ₹2700 CrUtilization: 65.9%Overrun: +₹145 Cr

Original Cost

₹2555 Cr

Baseline estimate

+6% overrun

Revised Cost

₹2700 Cr

Latest approved cost

Expenditure

₹1780 Cr

Spent to date

Utilization

65.9%

Of revised budget

Escalated

Cost Status

+5.7%

+₹145 Cr increase

Remaining

₹921 Cr

Budget left

Budget Utilization

65.9%
0%25%50%75%100%

Spent

₹1780 Cr

Remaining

₹921 Cr

Total

₹2700 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2555 Cr

Revised Cost

₹2700 Cr

Increase

+₹145 Cr

Escalation

+5.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2028

Revised Completion

31/03/2028

Completed

Project Details

Project Code705385
SectorRailways
MinistryMinistry of Railways
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹2555 Cr
Revised Cost₹2700 Cr
Expenditure₹1780 Cr
Original End Date31/03/2028
Revised Date31/03/2028

Project Intelligence

Cost has increased by ₹145 Cr (5.7%) from the original estimate of ₹2555 Cr.

Expenditure stands at ₹1780 Cr, which is 65.9% of the revised project cost.

Remaining budget: ₹921 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Pirpainti - Jasidih 97 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2555.00 Cr, later revised to ₹2700.43 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pirpainti - Jasidih 97 km"?
Pirpainti - Jasidih 97 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Jharkhand. Original cost: ₹2555 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2555 Cr and has been revised to ₹2700 Cr — a cost overrun of +5.7%. Expenditure to date: ₹1780 Cr (65.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Pirpainti - Jasidih 97 km is under the Ministry of Railways in the Railways sector. Project code: 705385. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pirpainti - Jasidih 97 km is one of several Bihar projects tracked under the Railways sector on the IPM system.