Roads & HighwaysIPM · Central Project +58.4% overrun#618699

Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1297 CrUtilization: 14.5%Overrun: +₹478 Cr

Original Cost

₹819 Cr

Baseline estimate

+58% overrun

Revised Cost

₹1297 Cr

Latest approved cost

Expenditure

₹189 Cr

Spent to date

Utilization

14.5%

Of revised budget

Escalated

Cost Status

+58.4%

+₹478 Cr increase

Remaining

₹1109 Cr

Budget left

Budget Utilization

14.5%
0%25%50%75%100%

Spent

₹189 Cr

Remaining

₹1109 Cr

Total

₹1297 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹819 Cr

Revised Cost

₹1297 Cr

Increase

+₹478 Cr

Escalation

+58.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/09/2021

Revised Completion

Completed

Project Details

Project Code618699
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-05

Financial Summary

Original Cost₹819 Cr
Revised Cost₹1297 Cr
Expenditure₹189 Cr
Original End Date03/09/2021
Revised DateN/A

Project Intelligence

Cost has increased by ₹478 Cr (58.4%) from the original estimate of ₹819 Cr.

Expenditure stands at ₹189 Cr, which is 14.5% of the revised project cost.

Remaining budget: ₹1109 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹819.00 Cr, later revised to ₹1297.38 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328"?
Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹819 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹819 Cr and has been revised to ₹1297 Cr — a cost overrun of +58.4%. Expenditure to date: ₹189 Cr (14.5% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618699. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.