Original Cost
₹1178 Cr
Baseline estimate
Revised Cost
₹1777 Cr
Latest approved cost
Expenditure
₹1490 Cr
Spent to date
Utilization
83.8%
Of revised budget
Cost Status
+50.8%
+₹599 Cr increase
Remaining
₹288 Cr
Budget left
Spent
₹1490 Cr
Remaining
₹288 Cr
Total
₹1777 Cr
Original Cost
₹1178 Cr
Revised Cost
₹1777 Cr
Increase
+₹599 Cr
Escalation
+50.8%
Project Approved
Construction / Implementation
Original End Date
31/12/2024
Revised Completion
31/03/2026
Completed
Cost has increased by ₹599 Cr (50.8%) from the original estimate of ₹1178 Cr.
Expenditure stands at ₹1490 Cr, which is 83.8% of the revised project cost.
Remaining budget: ₹288 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.