rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 Total length 80.00Km
Original Cost
₹227 Cr
Baseline estimate
Revised Cost
₹321 Cr
Latest approved cost
Expenditure
₹224 Cr
Spent to date
Utilization
69.8%
Of revised cost
Cost Overrun
+41.5%
+₹94 Cr
Remaining
₹97 Cr
Budget left
Spent
₹224 Cr
Remaining
₹97 Cr
Total
₹321 Cr
69.8%
Utilized
Original Cost
₹227 Cr
Revised Cost
₹321 Cr
Increase
+₹94 Cr
Escalation
+41.5%
Project Approved
Construction / Implementation
Original End Date
2025-12-11
Revised Completion
2026-07-27
Completed
Cost has increased by ₹94 Cr (41.5%) from the original estimate of ₹227 Cr.
Expenditure stands at ₹224 Cr, which is 69.8% of the revised project cost.
Remaining budget: ₹97 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.