Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 Total Length of 79.085 Km of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 Total length 80.00Km
Original Cost
₹227 Cr
Baseline estimate
Revised Cost
₹321 Cr
Latest approved cost
Expenditure
₹234 Cr
Spent to date
Utilization
72.8%
Of revised budget
Cost Status
+41.5%
+₹94 Cr increase
Remaining
₹87 Cr
Budget left
Budget Utilization
72.8%Spent
₹234 Cr
Remaining
₹87 Cr
Total
₹321 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹227 Cr
Revised Cost
₹321 Cr
Increase
+₹94 Cr
Escalation
+41.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
11/12/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹94 Cr (41.5%) from the original estimate of ₹227 Cr.
Expenditure stands at ₹234 Cr, which is 72.8% of the revised project cost.
Remaining budget: ₹87 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 Total Length of 79.085 Km of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 Total length 80.00Km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹227.00 Cr, later revised to ₹321.23 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P"?
- Permanent rectification of 3 nos. of black spots in project Highway NH-27 of U.P border - Dewapur - Kotwa section from Km.360.915 to km.440.000 Total Length of 79.085 Km of NH-27& Permanent rectification of 5 nos. of black spots of project Highway NH-27 of Kotwa - Mehsi - Muzaffarpur Section from km.440.000 to km.520.000 Total length 80.00Km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹227 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹227 Cr and has been revised to ₹321 Cr — a cost overrun of +41.5%. Expenditure to date: ₹234 Cr (72.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Permanent rectification of 3 nos. of black spots in project is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618571. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Permanent rectification of 3 nos. of black spots in project is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.