Penukonda - Dharmavaram Doubling Project [41.5 Km]

Ministry of RailwaysAndhra Pradesh
Revised Cost: ₹308 CrUtilization: 96.4%

Original Cost

₹308 Cr

Baseline estimate

On budget

Revised Cost

₹308 Cr

Latest approved cost

Expenditure

₹297 Cr

Spent to date

Utilization

96.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹11 Cr

Budget left

Budget Utilization

96.4%
0%25%50%75%100%

Spent

₹297 Cr

Remaining

₹11 Cr

Total

₹308 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2026

Revised Completion

31/03/2026

Completed

Project Details

Project Code705789
SectorRailways
MinistryMinistry of Railways
StateAndhra Pradesh
Data Month2026-01

Financial Summary

Original Cost₹308 Cr
Revised Cost₹308 Cr
Expenditure₹297 Cr
Original End Date31/03/2026
Revised Date31/03/2026

Project Intelligence

Project is within original budget of ₹308 Cr — no cost escalation recorded.

Expenditure stands at ₹297 Cr, which is 96.4% of the revised project cost.

Remaining budget: ₹11 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Penukonda - Dharmavaram Doubling Project [41.5 Km] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹308.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Penukonda - Dharmavaram Doubling Project [41.5 Km]"?
Penukonda - Dharmavaram Doubling Project [41.5 Km] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Andhra Pradesh. Original cost: ₹308 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹308 Cr and has been revised to ₹308 Cr — a cost overrun of -0.1%. Expenditure to date: ₹297 Cr (96.4% of revised cost). Data as of 2026-01.
QWhich ministry is responsible for this project?
Penukonda - Dharmavaram Doubling Project [41.5 Km] is under the Ministry of Railways in the Railways sector. Project code: 705789. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Penukonda - Dharmavaram Doubling Project [41.5 Km] is one of several Bihar projects tracked under the Railways sector on the IPM system.