Original Cost
₹336 Cr
Baseline estimate
Revised Cost
₹336 Cr
Latest approved cost
Expenditure
₹74 Cr
Spent to date
Utilization
22.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹262 Cr
Budget left
Spent
₹74 Cr
Remaining
₹262 Cr
Total
₹336 Cr
Project Approved
Construction / Implementation
Original End Date
01/04/2024
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹336 Cr — no cost escalation recorded.
Expenditure stands at ₹74 Cr, which is 22.1% of the revised project cost.
Remaining budget: ₹262 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.