Original Cost
₹955 Cr
Baseline estimate
Revised Cost
₹2094 Cr
Latest approved cost
Expenditure
₹130 Cr
Spent to date
Utilization
6.2%
Of revised budget
Cost Status
+119.2%
+₹1139 Cr increase
Remaining
₹1963 Cr
Budget left
Spent
₹130 Cr
Remaining
₹1963 Cr
Total
₹2094 Cr
Original Cost
₹955 Cr
Revised Cost
₹2094 Cr
Increase
+₹1139 Cr
Escalation
+119.2%
Project Approved
Construction / Implementation
Original End Date
31/08/2027
Revised Completion
28/03/2028
Completed
Cost has increased by ₹1139 Cr (119.2%) from the original estimate of ₹955 Cr.
Expenditure stands at ₹130 Cr, which is 6.2% of the revised project cost.
Remaining budget: ₹1963 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.