Original Cost
₹648 Cr
Baseline estimate
Revised Cost
₹648 Cr
Latest approved cost
Expenditure
₹208 Cr
Spent to date
Utilization
32.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹440 Cr
Budget left
Spent
₹208 Cr
Remaining
₹440 Cr
Total
₹648 Cr
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹648 Cr — no cost escalation recorded.
Expenditure stands at ₹208 Cr, which is 32.1% of the revised project cost.
Remaining budget: ₹440 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.