Original Cost
₹4830 Cr
Baseline estimate
Revised Cost
₹4830 Cr
Latest approved cost
Expenditure
₹3351 Cr
Spent to date
Utilization
69.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1479 Cr
Budget left
Spent
₹3351 Cr
Remaining
₹1479 Cr
Total
₹4830 Cr
Project Approved
Construction / Implementation
Original End Date
31/08/2026
Revised Completion
31/03/2029
Completed
Project is within original budget of ₹4830 Cr — no cost escalation recorded.
Expenditure stands at ₹3351 Cr, which is 69.4% of the revised project cost.
Remaining budget: ₹1479 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.